Join the 155,000+ IMP followers

railway-international.com
HS2 News

HS2 REVEALS FIRST GIANT LAKE PIERS FOR RECORD-BREAKING COLNE VALLEY VIADUCT

On the first anniversary of the start of deck construction for the UK’s longest railway bridge, HS2 reveals the first enormous lake piers that will carry the 2-mile viaduct across a series of waterways on the outskirts of London.

HS2 REVEALS FIRST GIANT LAKE PIERS FOR RECORD-BREAKING COLNE VALLEY VIADUCT

One year after the launch of HS2’s giant ‘bridge-building machine’, progress on the UK’s longest railway bridge has taken another major step forward with the completion of the first piers that will carry the viaduct over a series of lakes just outside London.

The Colne Valley Viaduct – which is being built near Hillingdon - will carry high-speed trains more than two miles (3.4km) across the Grand Union Canal, River Colne, local roads and a series of lakes between the end of the London tunnels and the start of the Chiltern tunnels.

For the last year, a 700-tonne ‘launch girder’ – the only one of its kind in the UK - has been assembling giant pre-cast concrete segments to form the first 1 km of the viaduct deck along the edge of the valley. Now, the first enormous v-shaped piers have been completed in the lake, to allow the viaduct to curve eastward, over the water. The ‘V piers’ – each weighing in at 1,800 tonnes – will support a row of elegant arches inspired by the flight of a stone skimming over the surface of the water.

To allow for the gentle curve of the viaduct, each of the one thousand segments that form the arches and deck is slightly different – and all are manufactured at a temporary factory set up close by, with direct access to the M25. Designed to bear the weight of the 80m wide arches over the lakes, the ‘v-piers’ are twice as large as simpler piers that carry the viaduct over land.

Cast in place using a series of giant moulds, each pier has a separate tower crane, with a temporary access bridge linking them with the main construction site. Cofferdams were used to hold back the water while the 60m deep foundations were built into the bed of the lakes. Each pier weighs around 1,800 tonnes and took nine months to complete. To help the engineers master the complex shape of the pier, a mock-up was built off site before work began on the real piers. In total, 11 ‘v-piers’ will support the viaduct over water with a further 45 piers on land.

Once the piers are ready, deck segments will be placed alternately on each side, using a cantilever approach to balance the structure, as two half-arches are constructed simultaneously. Steel tensioning cables are then threaded through the segments to strengthen the bridge.

www.hs2.org.uk

  Ask For More Information…

LinkedIn
Pinterest

Join the 155,000+ IMP followers