Join the 155,000+ IMP followers

railway-international.com
HS2 News

HS2 welcomes planning approval for major Birmingham viaducts

HS2 Ltd has been granted Schedule 17 consent by Birmingham City Council for two viaducts which will take the new high speed railway into Curzon Street Station in the city centre.

HS2 welcomes planning approval for major Birmingham viaducts
HS2 welcomes planning approval for major Birmingham viaducts: HS2 Curzon No.3 Viaduct CGI from below

Curzon Viaduct No.3 and Lawley Middleway Viaduct are part of the Curzon Street Station Approach area, which is made up of four connected viaducts between Duddeston Junction Viaduct and Curzon Street Station in central Birmingham. The other viaducts are Curzon Street No.1 Viaduct (furthest from the station) and Curzon Street No.2 Viaduct.

A number of design refinements have resulted in a shorter construction programme and less concrete needed to build the viaduct, bringing positive environmental and community benefits.

The viaducts are being designed by a Design Joint Venture of Mott MacDonald and Systra and architects Weston Williamson + Partners, all working for HS2’s civils contractor Balfour Beatty VINCI joint venture.

David Speight, Client Project Director at HS2 Ltd said:
“We are very pleased that Birmingham City Council’s planning committee approved the plans for these viaducts. This decision represents a significant approval for HS2 in Birmingham city centre and means we are on track to bring high speed rail to the West Midlands, increasing capacity and connectivity across the UK. In addition, our design refinements on the viaducts will bring a range of extra benefits, including reducing the construction time and materials, reducing the amount of carbon we need on the project.”

Nick Robertshaw, Project Manager from the Design Joint Venture Mott MacDonald and Systra said:
“BBV and the DJV design team have brought their global expertise to tackle the significant engineering challenges involved in fulfilling HS2’s design vision for this iconic structure, which will provide a catalyst for social and economic development.

“This landmark milestone for the programme has only been made possible through the ‘one team approach’ facilitated by HS2 with Birmingham City Council, whose critical input and collaboration has enabled this achievement.”

Nick McGough, Director at Weston Williamson and Partners said:
“The key design challenge of Curzon 3 was to address varied sites with differing technical requirements whilst providing both a level of consistency as well as ensuring the viaduct contributes positively to its surroundings. Toward the HS2 Curzon Street Station the viaduct is over 60m wide and so the design maximises daylight under the structure through the introduction of light slots with a unique lightweight parapet design. Over the Digbeth Canal the opportunity is taken to reference Birmingham’s canalside heritage whilst the large span required over Lawley Middleway is achieved through the use of heroic weathering steel girders which arch over the carriageway.

“This has only been possible through the close collaboration between architect, engineer, and construction team and Birmingham City Council’s support of the result is testament that this 21st Century structure will contribute positively to the local community and allow for unique spaces that will add to the life of the city.”

The Curzon Viaduct No.3 is approximately 300 metres long, the height above ground level varies between 5 metres to 6 metres, it is 65 metres wide at the widest point and will be supported by 30 piers. As it approaches Curzon Street Station, the deck of the viaduct widens from a single deck at the eastern end to four separate decks at the western end.

The viaduct will widen to four separate decks near Curzon Street Station to maximise daylight in the public space underneath. V piers have been developed to support the viaducts because they take up less room at ground level and will also have a side recess for future potential services to be visually integrated. As well as separating the viaduct into four separate decks, the V piers will also help to maximise the opportunities to create a usable and flexible public space under the viaduct.

As Curzon Street No.3 Viaduct crosses the Digbeth Canal, the concrete V piers are substituted with four inverted steel piers which reference the heritage of canal-side cranes in Birmingham. This also means the Digbeth Canal area will remain a visually attractive area to the public, combining the twenty first century HS2 infrastructure and the nineteenth century Digbeth Canal area, ensuring a positive legacy for this part of the city.

Through the development of the designs, the width of the viaduct has been reduced from 71 metres to 65 metres. The Curzon Street Pumping Station that was previously located south of the viaduct has been removed from the design as water that gathers on the viaduct will now be drained into either an attenuation pond - an area on the ground that temporarily stores excess water before releasing it in a controlled way, or attenuation tank located underground.

www.hs2.com

  Ask For More Information…

LinkedIn
Pinterest

Join the 155,000+ IMP followers